Construction progress

30.09.2026

Construction Progress for September 2026

Section 1:

  • Tower crane installation — 100%
  • Construction of the monolithic reinforced concrete frame — 30%

Section 2:

  • Tower crane installation — 100%
  • Construction of the monolithic reinforced concrete frame — 7%

Section 3:

  • Excavation works — 100%

Shelter 1:

  • Excavation works — 100%
  • Base preparation and concrete blinding — 100%
  • Foundation slab construction — 100%
  • Construction of monolithic protective walls and floor slab — 98%
  • External waterproofing and backfilling — 55%