Construction Progress for July 2026
Section 1:
- First floor: monolithic works fully completed
- Second floor: reinforcement works are underway, followed by concreting
- Shelter in Section 1: monolithic works have been completed; preparation of the walls for external waterproofing is underway
Section 2:
- Foundation works completed
- Concrete pouring of the basement-level walls is underway
Section 3:
- Foundation pit completed