Construction progress

31.10.2026

Construction Progress for October 2026

Section 1:

  • Construction of the monolithic reinforced concrete frame — 40%

Section 2:

  • Construction of the monolithic reinforced concrete frame — 12%

Section 3:

  • Pile foundation installation — 100%

Shelter No. 1:

  • Construction of monolithic protective walls and floor slab — 98%
  • External waterproofing and backfilling — 58%