Construction progress

31.08.2026

Construction Progress for August 2026

Section 1:

  • Pile foundation works – 100%
  • Foundation base preparation
    (concrete blinding, waterproofing) – 100%
  • Foundation slab construction – 100%
  • Tower crane installation
  • Construction of the monolithic
    reinforced concrete frame – 22%

Section 2:

  • Pile foundation works – 100%
  • Foundation base preparation
    (concrete blinding, waterproofing) – 100%
  • Foundation slab construction – 100%
  • Tower crane installation
  • Construction of the monolithic
    reinforced concrete frame – 3%

Section 3:

  • Excavation works – 100%